Home > Guide to Factory Installation Procedures > Septic Tank Act Profiles

Guide to Factory Installation Procedures

Septic Tank Act

Followings are applicable when procedures based on laws or ordinances, etc. are required.
Name of laws and regulations Septic Tank Act
When
(The timing of procedures)
Prior to the installation of septic tanks.
Who
(Procedure Targets)
Those who intend to install septic tanks (Septic Tank Administrator).
What
(Documents)
1. When install or modify its construction or size of the the septic tank certified by the Minister of Land, Infrastructure, Transport and Tourism pursuant to the provision of Article 13 of the Septic Tank Act.
  Documents specified by the Mayor of the municipality.

2. When install or modify its construction or size of the septic tank NOT certified by the Minister of Land, Infrastructure, Transport and Tourism pursuant to the provision of Article 13 of the Septic Tank Act.
 (1) Structural drawing
 (2) Specification document
 (3) Processing flow chart
 (4) Design calculation document
 (5) Listed documents from (2) to (6) on above paragraph 1.

For further details, please inquire to "Contact for Inquiries".
Where
(Procedure Office)
Municipal Environment Conservation Administrative Section in charge which ruling the place of the installation.
How
(Examination Contents)
Examine whether the notification complies with the requirements on submission, and the notification is accepted when conforms.
Flow of Procedures
Processing Period Within 21 days.
Contact for Inquiries Tochigi Prefecture Department of Industry, Labor and Tourism, International Section 
TEL: 028-623-2194 
FAX: 028-623-2199