Home > Guide to Factory Installation Procedures > Act Concerning Control etc. of Erosion Control Designated Areas (Erosion Control Act)

Guide to Factory Installation Procedures

Act Concerning Control etc. of Erosion Control Designated Areas (Erosion Control Act)

Followings are applicable when procedures based on laws or ordinances, etc. are required.
Name of laws and regulations Act Concerning Control etc. of Erosion Control Designated Areas (Erosion Control Act)
When
(The timing of procedures)
At any time.
Who
(Procedure Targets)
Those who intend to make following activities in erosion control designated areas.
・Digging , banking, or cutting of land, and other modification of the land configuration.
・Felling trees or bamboos.
・Disposals or deposits of soils and stones, sand gravel, or minerals.
・Transportations of trees and bamboos by sliding down or pulling.
・To do heating or brazing fire.
・New construction, reconstruction, or demolition of structures.
・Use of erosion facilities.
・Extraction of soils and stones, sand gravel, lawn grass.
What
(Documents)
・Erosion Control Designated Area Action Permission Application.
Tochigi Prefecture Website Application Download Service
・Location drawings(a scale of 1:50,000)
・Business profiles explanation documents(describe the purpose and reason of action "Use" simply and appropriately).
・Business influences measures(describe the effects of the erosion control in flood control simply and appropriately).
・Actual measured plane drawing (Basically a scale of 1:1,000).
・Registered map and designated area registered map.
・Actual measured cross section (Basically a scale of 1:1,000).
・Actual measured longitudinal section (scale and slope shall be described accurately).
・Structure Structural Drawing (Basically a scale of 1:1,000).
・Actual measured area calculated drawing (about a scale of 1:500).
・Calculation documents (summarized data by the number of the type of construction type)
・Current status photos.
・Acknowledgement, etc. of interested parties.

<Some of the above documents may not be required depends on the contents of applications.> For further details, please inquire to "Contact for Inquiries".
Where
(Procedure Office)
Engineering office ruling the erosion control designated area.
(Depends on the contents of the application, submit via Civil Engineering Office to Tochigi Prefecture Prefectural Land Development Department Erosion Control Water Resource Section.)
How
(Examination Contents)
To examine submitted documents whether the contents of applications are not harmful from the stand point of flood controls and erosion controls.
Flow of Procedures
Processing Period Approximately 3 〜 6 weeks.
Contact for Inquiries Tochigi Prefecture Department of Industry, Labor and Tourism, International Section 
TEL: 028-623-2194 
FAX: 028-623-2199

Return to Top