Home > Guide to Factory Installation Procedures > Landslide, etc. Prevention Act Profiles

Guide to Factory Installation Procedures

Landslide, etc. Prevention Act

Followings are applicable when procedures based on laws or ordinances, etc. are required.
Name of laws and regulations Landslide, etc. Prevention Act
When
(The timing of procedures)
At any time.
Who
(Procedure Targets)
Those who intend to do following acts within landslide prevention areas.
・Acts to increase the underground water by attracting or stagnating underground water, or to disturb the functions of the drainage facilities and other acts to disturb the drainage of underground water.
・Acts to drain or stagnate ground surface water, or other acts to encourage the penetration of ground surface water.
・Cutting of slope surface, cutting of land specified by Cabinet Order.
・New construction or improvement of reservoir, waterway, or other facilities or structures except landslide prevention facilities. which specified by Cabinet Order
・Acts to disturb the prevention of landslide, or to encourage or induce landslide, and specified by Cabinet Order.
What
(Documents)
・Application.
・Location drawing (a scale of 1:50,000).
・Business Profiles Explanations
・Actual measured plane view (principally a scale of more than 1:1,000).
・Registered map and designated area registered map.
・Actual measured volume calculation drawing (about a scale of 1:500).
・Actual structural drawing (principally a scale of 1: 100).
・Actual measured cross section (Basically a scale of 1:1,000).
・Actual measured longitudinal section (scale and slope shall be described accurately).
・Current status photos.
<Some of the above documents may not be required depends on the contents of applications.>
For further details please inquire to 「Contact for Inquiries」.
Where
(Procedure Office)
Civil Engineering Office controlling the landslide prevention areas.
How
(Examination Contents)
To examine the submitted documents whether the activities may encourage or induce a landslide or collapse of coal mountain.
Flow of Procedures
Processing Period Approximately 6 weeks.
Contact for Inquiries Tochigi Prefecture Department of Industry, Labor and Tourism, International Section 
TEL: 028-623-2194 
FAX: 028-623-2199