Home > Guide to Factory Installation Procedures > City Planning Act Profiles

Guide to Factory Installation Procedures

City Planning Act

Followings are applicable when procedures based on laws or ordinances, etc. are required.
Name of laws and regulations City Planning Act
When
(The timing of procedures)
When carrying our development or acquisition of land. And whenmaking new construction or extension of buildings.
Who
(Procedure Targets)
1. Those who intend to develop 1,000 u or more area in the urbanization promotion areas.
2. Those who intend to make development acts in the urbanization control areas.
3. Those who intend to develop 3,000u (at Utsunomiya and Nikko, 1,000 u or more) or more within the non-delineated areas.
4. Those who intend to develop 1 ha. or more area outside the city planning areas.
What
(Documents)
・Development Activities Permission Application
・Development Activities Change Permission Application Download
・Place for Submission and Attached Documents
Where
(Procedure Office)
Each Civil Engineering Office. However in Utsunomiya, Ashikaga, Tochigi, Sano, Kanuma, , and Oyama, to the supervisory section of each city.
How
(Examination Contents)
Flow of Procedures
Processing Period Please refer to 『Flow of Procedures』
Contact for Inquiries Tochigi Prefecture Department of Industry, Labor and Tourism, International Section 
TEL: 028-623-2194 
FAX: 028-623-2199