Home >  Guide to Factory Installation Procedures >  Tochigi Prefectural Natural Park Act Profiles

Guide to Factory Installation Procedures

Tochigi Prefectural Natural Park Act

Followings are applicable when procedures based on laws or ordinances, etc. are required.
Name of laws and regulations Tochigi Prefectural Natural Park Act
When
(The timing of procedures)
Prior to the commencement of acts.
Who
(Procedure Targets)
Those who modify land configuration of factory site, and newly build, reform, or expand factories, etc. in prefectural natural parks.
What
(Documents)
In the special areas, a New Construction (or reform, or expansion) of Structure in Special Areas Application describing the purpose of building structure, place, situation of the place of the act, type of the structure, construction method, planned date of the commencement of the construction, etc.
In the normal areas, a New Construction (or reform, or expansion) of Structure in Normal Areas Application.
For the application form, please contact to each municipality.
Where
(Procedure Office)
Each municipal section in charge ( Authority had been transferred to municipalities since April 1,2010).
How
(Examination Contents)
Relationships with the park planning, status of the place of the acts and its surroundings, propriety of development method, effect on scenic beauty and landscape or surrounding environment of the place of the acts, conditions when it is permitted, situation of measures by other laws and regulations, consent of the land owner, and other items necessary to determine the permission are examined.
Flow of Procedures
Processing Period Approximately 1 month.
Contact for Inquiries Tochigi Prefecture Department of Industry, Labor and Tourism, International Section 
TEL: 028-623-2194 
FAX: 028-623-2199